District Projects

Lexington

Lexington
5
TOTAL
0
NEW
2
ACTIVE
3
COMPLETE
Fiske

Type: Waitlist

Phase: Final Audit Approved

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Completed
Joseph Estabrook

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 37.27%

Total Budget: $43,392,248

Est. Max Total Facilities Grant *: $12,148,491

Est. Completion:

Completed
Lexington High

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 33.95%

Total Budget: $1,197,444

Est. Max Total Facilities Grant *: $0

Est. Completion:

Completed
Lexington High

Type: Core Program

Phase: Approved Project Vote Pending

Reimbursement Rate: 31.00%

Total Budget: $1,825,000

Est. Max Total Facilities Grant *: $0

Est. Completion:

Active
Maria Hastings

Type: Core Program

Phase: Closeout

Reimbursement Rate: 35.79%

Total Budget: $65,279,417

Est. Max Total Facilities Grant *: $16,513,723

Est. Completion: February, 2020

Active