Marshfield

Marshfield
4
TOTAL
1
ACTIVE
3
COMPLETE
Furnace Brook Middle
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 48.47%

Total Budget: $8,503,235

Est. Max Total Facilities Grant *: $2,106,340

Est. Completion:

Gov Edward Winslow
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 46.37%

Total Budget: $2,137,791

Est. Max Total Facilities Grant *: $0

Est. Completion:

Marshfield High
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 55.61%

Total Budget: $101,630,087

Est. Max Total Facilities Grant *: $46,550,599

Est. Completion:

Martinson Elementary
Active

Type: Accelerated Repair

Phase: Approved Project Vote Pending

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion: