A E Angier
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 40.10%

Total Budget: $37,491,546

Est. Max Total Facilities Grant *: $10,687,077

Est. Completion: December, 2015

Bigelow Middle
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 32.47%

Total Budget: $1,364,006

Est. Max Total Facilities Grant *: $352,580

Est. Completion: August, 2019

Bowen
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 35.42%

Total Budget: $167,475

Est. Max Total Facilities Grant *: $0

Est. Completion:

Cabot
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 40.22%

Total Budget: $48,994,618

Est. Max Total Facilities Grant *: $13,636,546

Est. Completion: June, 2019

Carr School
Active

Type: Core Program

Phase: N/A

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Countryside
Active

Type: Core Program

Phase: Construction

Reimbursement Rate: 36.79%

Total Budget: $72,232,012

Est. Max Total Facilities Grant *: $20,214,455

Est. Completion: June, 2027

F A Day Middle
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 32.47%

Total Budget: $1,160,066

Est. Max Total Facilities Grant *: $272,104

Est. Completion: September, 2020

Newton North High
Completed

Type: Waitlist

Phase: Final Audit Approved

Reimbursement Rate: 60.00%

Total Budget: $197,499,511

Est. Max Total Facilities Grant *: $0

Est. Completion:

Williams
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 35.42%

Total Budget: $301,900

Est. Max Total Facilities Grant *: $0

Est. Completion: