MSBA Logo

Massachusetts School Building Authority

District Projects

Springfield

Springfield
69
TOTAL
18
ACTIVE
51
COMPLETE
Alfred G Zanetti
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,681,143

Est. Max Total Facilities Grant *: $2,016,205

Est. Completion:

Alice B Beal Elementary
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $678,333

Est. Max Total Facilities Grant *: $0

Est. Completion:

Alice B Beal Elementary
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,086,852

Est. Max Total Facilities Grant *: $0

Est. Completion:

Arthur T Talmadge
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $63,669

Est. Max Total Facilities Grant *: $0

Est. Completion:

Benjamin Swan Elementary
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $539,352

Est. Max Total Facilities Grant *: $0

Est. Completion:

Brightwood
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $80,624,011

Est. Max Total Facilities Grant *: $49,147,673

Est. Completion: August, 2021

Daniel B Brunton
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,662,470

Est. Max Total Facilities Grant *: $1,680,701

Est. Completion: August, 2017

Dryden Memorial
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 100.00%

Total Budget: $15,051,832

Est. Max Total Facilities Grant *: $0

Est. Completion: August, 2013

Dryden Memorial
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Elias Brookings
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 100.00%

Total Budget: $27,900,000

Est. Max Total Facilities Grant *: $25,563,992

Est. Completion: January, 2015

Forest Park Middle
Completed

Type: Waitlist

Phase: Final Audit Approved

Reimbursement Rate: 90.00%

Total Budget: $44,144,993

Est. Max Total Facilities Grant *: $0

Est. Completion:

Frank H Freedman
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,675,168

Est. Max Total Facilities Grant *: $0

Est. Completion:

Frederick Harris
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,165,201

Est. Max Total Facilities Grant *: $749,722

Est. Completion: September, 2021

German Gerena Community
Active

Type: Core Program

Phase: Feasibility Study

Reimbursement Rate: 80.00%

Total Budget: $2,500,000

Est. Max Total Facilities Grant *: $0

Est. Completion:

German Gerena Community
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,414,794

Est. Max Total Facilities Grant *: $0

Est. Completion:

Glenwood
Active

Type: Accelerated Repair

Phase: N/A

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Glickman Elementary
Active

Type: Accelerated Repair

Phase: Closeout

Reimbursement Rate: 80.00%

Total Budget: $3,536,642

Est. Max Total Facilities Grant *: $2,138,260

Est. Completion:

Glickman Elementary
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,486,902

Est. Max Total Facilities Grant *: $0

Est. Completion:

High Of Commerce
Active

Type: Accelerated Repair

Phase: Design Development

Reimbursement Rate: 80.00%

Total Budget: $16,555,067

Est. Max Total Facilities Grant *: $8,952,502

Est. Completion:

Indian Orchard Elementary
Active

Type: Accelerated Repair

Phase: Design Development

Reimbursement Rate: 80.00%

Total Budget: $7,483,632

Est. Max Total Facilities Grant *: $4,555,971

Est. Completion:

Indian Orchard Elementary
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $715,710

Est. Max Total Facilities Grant *: $510,462

Est. Completion: September, 2021

John F Kennedy Middle
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $4,487,803

Est. Max Total Facilities Grant *: $2,096,906

Est. Completion: December, 2015

John F Kennedy Middle
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,781,796

Est. Max Total Facilities Grant *: $0

Est. Completion:

John J Duggan Academy
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $5,220,014

Est. Max Total Facilities Grant *: $0

Est. Completion:

Kensington International
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,222,828

Est. Max Total Facilities Grant *: $748,320

Est. Completion: August, 2016

Kensington International
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,488,913

Est. Max Total Facilities Grant *: $1,091,826

Est. Completion:

Kiley Academy
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $6,414,070

Est. Max Total Facilities Grant *: $4,763,458

Est. Completion:

Kiley Academy
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,478,567

Est. Max Total Facilities Grant *: $0

Est. Completion:

Liberty
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $684,327

Est. Max Total Facilities Grant *: $0

Est. Completion:

Margaret C Ells
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,341,047

Est. Max Total Facilities Grant *: $0

Est. Completion:

Margaret C Ells
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,218,912

Est. Max Total Facilities Grant *: $865,882

Est. Completion: August, 2014

Mary M Lynch
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $990,659

Est. Max Total Facilities Grant *: $0

Est. Completion:

Mary M Lynch
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,504,816

Est. Max Total Facilities Grant *: $1,128,774

Est. Completion:

Mary M Walsh
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $819,836

Est. Max Total Facilities Grant *: $0

Est. Completion:

Mary M Walsh
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,646,869

Est. Max Total Facilities Grant *: $1,405,767

Est. Completion: August, 2017

Mary O Pottenger
Completed

Type: Core Program

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Mary O Pottenger
Active

Type: Accelerated Repair

Phase: Design Development

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Milton Bradley
Active

Type: Accelerated Repair

Phase: Closeout

Reimbursement Rate: 80.00%

Total Budget: $2,171,702

Est. Max Total Facilities Grant *: $978,010

Est. Completion:

Milton Bradley
Active

Type: Accelerated Repair

Phase: Design Development

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Milton Bradley
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,119,205

Est. Max Total Facilities Grant *: $1,539,360

Est. Completion:

Milton Bradley
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $767,533

Est. Max Total Facilities Grant *: $0

Est. Completion:

Putnam Vocational Technical Academy
Completed

Type: Waitlist

Phase: Final Audit Approved

Reimbursement Rate: 90.00%

Total Budget: $114,303,152

Est. Max Total Facilities Grant *: $0

Est. Completion: July, 2012

Rebecca M Johnson
Active

Type: Accelerated Repair

Phase: Design Development

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Rebecca M Johnson
Active

Type: Accelerated Repair

Phase: Closeout

Reimbursement Rate: 80.00%

Total Budget: $1,712,203

Est. Max Total Facilities Grant *: $910,570

Est. Completion:

Rebecca M Johnson
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $696,052

Est. Max Total Facilities Grant *: $0

Est. Completion:

Samuel Bowles
Active

Type: Accelerated Repair

Phase: Design Development

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

South End Middle
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,654,585

Est. Max Total Facilities Grant *: $1,154,238

Est. Completion:

South End Middle
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $478,001

Est. Max Total Facilities Grant *: $323,864

Est. Completion: August, 2014

Springfield Central High
Active

Type: Green Repair

Phase: N/A

Reimbursement Rate: 80.00%

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Springfield Central High
Completed

Type: Science Lab Initiative

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $27,935,421

Est. Max Total Facilities Grant *: $0

Est. Completion:

Springfield Central High
Active

Type: Accelerated Repair

Phase: Design Development

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Springfield Central High
Active

Type: Accelerated Repair

Phase: Closeout

Reimbursement Rate: 80.00%

Total Budget: $2,048,991

Est. Max Total Facilities Grant *: $1,214,910

Est. Completion:

Springfield High of Science and Technology
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $4,760,969

Est. Max Total Facilities Grant *: $3,425,095

Est. Completion:

Springfield High of Science and Technology
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $3,918,000

Est. Max Total Facilities Grant *: $1,856,486

Est. Completion: October, 2020

Springfield High of Science and Technology
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,816,955

Est. Max Total Facilities Grant *: $1,910,628

Est. Completion: August, 2014

Springfield Legacy Academy
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,208,697

Est. Max Total Facilities Grant *: $1,297,364

Est. Completion: October, 2014

Springfield Middle
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,187,077

Est. Max Total Facilities Grant *: $773,433

Est. Completion:

Springfield Public Day High
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,690,808

Est. Max Total Facilities Grant *: $1,094,334

Est. Completion: August, 2017

Springfield Public Day High
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $819,439

Est. Max Total Facilities Grant *: $568,175

Est. Completion: August, 2014

Springfield Public Day High
Active

Type: Core Program

Phase: N/A

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

STEM Middle Academy
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,103,396

Est. Max Total Facilities Grant *: $1,037,297

Est. Completion: September, 2017

Sumner Avenue
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $680,206

Est. Max Total Facilities Grant *: $479,812

Est. Completion: September, 2021

Sumner Avenue
Active

Type: Accelerated Repair

Phase: Design Development

Reimbursement Rate:

Total Budget:

Est. Max Total Facilities Grant *: $0

Est. Completion:

Thomas M Balliet
Active

Type: Accelerated Repair

Phase: Closeout

Reimbursement Rate: 80.00%

Total Budget: $2,258,040

Est. Max Total Facilities Grant *: $1,206,581

Est. Completion:

Thomas M Balliet
Completed

Type: Accelerated Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $2,180,974

Est. Max Total Facilities Grant *: $1,564,966

Est. Completion:

Warner
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $1,532,958

Est. Max Total Facilities Grant *: $0

Est. Completion:

Washington
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $131,071

Est. Max Total Facilities Grant *: $0

Est. Completion:

White Street
Completed

Type: Green Repair

Phase: Final Audit Approved

Reimbursement Rate: 80.00%

Total Budget: $794,491

Est. Max Total Facilities Grant *: $0

Est. Completion:

William N. DeBerry
Active

Type: Core Program

Phase: Closeout

Reimbursement Rate: 80.00%

Total Budget: $94,366,017

Est. Max Total Facilities Grant *: $52,770,493

Est. Completion: June, 2023

An unhandled error has occurred. Reload 🗙