Type: Accelerated Repair
Phase: Final Audit Approved
Reimbursement Rate: 52.69%
Total Budget: $383,630
Est. Max Total Facilities Grant *: $187,541
Est. Completion: August, 2019
Type: Core Program
Phase: Schematic Design
Reimbursement Rate: 54.79%
Total Budget: $1,200,000
Est. Max Total Facilities Grant *: $0
Est. Completion:
Type: Core Program
Phase: Final Audit Approved
Reimbursement Rate: 49.74%
Total Budget:
Est. Max Total Facilities Grant *: $0
Est. Completion: August, 2008
Type: Accelerated Repair
Phase: Final Audit Approved
Reimbursement Rate: 52.69%
Total Budget: $1,339,458
Est. Max Total Facilities Grant *: $426,526
Est. Completion:
Type: Core Program
Phase: Final Audit Approved
Reimbursement Rate: 54.16%
Total Budget: $63,103,416
Est. Max Total Facilities Grant *: $26,385,058
Est. Completion: June, 2015